Tuesday, September 20, 2011

Bridge on the move

Today was a good day. The bridge is now resting on its concrete piers. It was manual labor with a ratcheting chain winch and two comelongs. I used the dozer as a fixed anchor point only. The move and positioning of the trusses was too delicate for brute diesel power.


I spent all day on the move, inch by inch it crept outward over the abyss. Help arrived in the afternoon when my son returned home from school and lend me a hand to finish the work. Im greatful for his help. Im blessed with two near adult sons that I lean on from time to time.

The work is far from done, as now I have to finish the positioning and anchor the bridge in place. Then its putting in the beams and deck.








Tuesday, June 28, 2011

Working on my truss bridge again.

Really I have been working on it off and on all spring into summer. But I thought to post an update on where Im at with it. There are to efforts going on at the same time, pier construction and truss fabrication.
Im in the first stages of laying out the scrap metal to see what the trusses will look like and make changes where needed. I then have to cut all the pieces to fit together and make ready for welding.



Most of my work has been on the center pier lately. Adding height to it in order to bring it level with both bank abutments. Laying courses of free salvage concrete blocks and filling in the center of the pier with rocks and rubble from the creek, I have built a solid center load bearing structure. Both the ends are made from 55 gallon barrels filled with rock and covered in concrete. Im thinking about covering the long faces of the pier with brick to match the abutments.



Tuesday, October 19, 2010

Bridge build photo update #4

My kids became some extra crew help a few weekends ago during the center pier concrete pour.



I pulled the flood damaged bridge frame out of the creek bed with the bulldozer. It will be cut up and used in the contruction of the new bridges steel truss frame.

Here are some more recent photos showing the start of the center pier and the west abutment.


A side shot showing all three now in various stages of construction.

Tuesday, September 21, 2010

More bridge building pics.

More bridge construction photos. East bank abutment. Since these photos were taken I have backfilled the wall, poured concrete for the upstream wing, and begun foundation work on the down stream wing.





Once all of the wing work is done on this side of the creek, I will pour a concrete slab over the wall and backfill. Then its off to the west side of the stream to do this again. I am also thinking of building a center pier to increse the bridge load carring ability.

Sunday, September 12, 2010

Pouring concrete today.


I was caught working on the bridge today.

Wednesday, June 16, 2010

Flash flood takes out my bridge!

Monday afternoon a huge line of thunderstorms tore through Indiana. Lots of wind, a few possible tornados, and massive quantities of rain. In a few hours, several inches of rain added to weeks of previous rainfall. It was too much for my old improvised steel frame bridge. The water spilled over the creek banks and swept up logs and debris. I had relied on this bridge for over ten years to cross this creek to get to my workshop trailer. Now I will be looking to push ahead with my plans to construct a larger bridge. One that a full sized truck can go over. I will keep all of you posted as I progress with it.